Question #142587

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?


Options:

Tags: Math
Answer: X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last 10 days.