Machine A can complete a job in 8 hours, and Machine B can complete the same job in 12 hours. If both machines work together, how many hours will they take to complete the job?


Options:

Tags: Math
Answer: Machine A can complete a job in 8 hours, and Machine B can complete the same job in 12 hours. If both machines work together, how many hours will they take to complete the job 4.8 hours.