Question #145382

Two classrooms are to be built in a school and planned that 8 masons and labours shall complete them is 20 days. If the number of workers is increased up to 10, how many days will be taken in the completion of work?


Options:

Tags: Math
Answer: Two classrooms are to be built in a school and planned that 8 masons and labours shall complete them is 20 days. If the number of workers is increased up to 10, how many days will be taken in the completion of work 16 days.

Question Screenshot

Question Screenshot
For best sharing results, download the image first and then attach it to your social media post.

Test Your Knowledge

Want to practice more questions like this? Take a quiz in this category!

Take a Quiz

Share This Question