Question #145432

A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?


Options:

Tags: Math
Answer: A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed 1 day.

Test Your Knowledge

Want to practice more questions like this? Take a quiz in this category!

Take a Quiz

Share This Question