A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately. If A begins first, in how many days the work will be completed ?


Options:

Answer: A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately. If A begins first, in how many days the work will be completed  41/4 days.