If the budgeted total direct labor hours are 5500 and budgeted direct labor cost is $755000, then the budgeted direct labor cost rate is _________?
Options:
Answer:
If the budgeted total direct labor hours are 5500 and budgeted direct labor cost is $755000, then the budgeted direct labor cost rate is 7.27 per hour.