If the fixed overhead allocated for actual output unit is $9800 and budgeted fixed overhead is $22000, then production volume variance would be _________?
Options:
Answer:
If the fixed overhead allocated for actual output unit is $9800 and budgeted fixed overhead is $22000, then production volume variance would be ,200.