The energy required per unit mass to grind limestone particles of very large size to 100 μm is 12.7 kWh/ton. An estimate (using Bond’s law) of the energy to grind the particles from a very large size to 50 μm is________________?
Options:
Answer:
The energy required per unit mass to grind limestone particles of very large size to 100 μm is 12.7 kWh/ton. An estimate (using Bond’s law) of the energy to grind the particles from a very large size to 50 μm is 18 kWh/ton.