Farjan and Kashif can complete a task in 30 days. Farjan leaves after 20 days and Kashif alone completes it in another 25 days. How many days does Farjan alone take to complete the entire task?
2
Jameel can complete a task in 15 hours and Nasir can complete the same task in 12 hours. Jameel starts the task at 9:00 am and stops working at 2:00pm. Nasir starts working on the task at 4:00 pm. At what time is the task completed?
3
P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in_________days.