Question #127866

The Horizontal distance between cutting and filling in earthwork is:


Options:

Explanation:
In earthwork engineering, Lead refers to the horizontal distance between the point of excavation (cutting) and the point of filling. It is used to calculate the cost and effort required to transport excavated material. The Lift, on the other hand, refers to the vertical distance. Both are key terms in earthwork quantity estimation and cost analysis.

Test Your Knowledge

Want to practice more questions like this? Take a quiz in this category!

Take a Quiz

Share This Question