A takes 6 days less than the time taken by B to finish a piece of work. If both A And B together can finish it in 4 days, find the time taken by B to finish the work.


Options:

Tags: Math
Answer: A takes 6 days less than the time taken by B to finish a piece of work. If both A And B together can finish it in 4 days, find the time taken by B to finish the work. 12.