If the budgeted price of input is $70, actual quantity of input is 250 units and the allowed budgeted quantity of input is 90 units, then efficiency variance will be ___________?


Options:

Answer: If the budgeted price of input is $70, actual quantity of input is 250 units and the allowed budgeted quantity of input is 90 units, then efficiency variance will be ,200.