Question #78058

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?


Options:

Answer: In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having least cost slope.